Price Rd and Brentwood Dr Culvert Replacements

CURRENT PROJECT STATUS UPDATE (November 29, 2022)

Price Road is complete, awaiting the guardrail installation. Once installed the road will be reopened to vehicle traffic. This was tentatively scheduled for this week, but may not be completed until the week of December 5th. 

At Brentwood Drive, the paving has been completed. The main items of work remaining are installation of the landscaping, stormwater curb, and guardrail. Guardrail will be installed right after the Contractor has completed it at Price Road, with curb and landscaping being installed over the next two weeks.

Traffic Impacts: 

  • Price Road - closure in place with detours for vehicles. Pedestrian and bicycles now may use the bridge. 
  • Brentwood Drive – roadway is open. During working hours expect one lane alternating traffic through the site with flaggers or the temporary signal.

Price Road and Brentwood DriveNovember 16, 2022 – Preparing to pave the south side of Brentwood Drive and the new bridge.

SCOPE

Both of the existing culverts for the two roadways are rated as blocking fish passage by WDFW, along with the culvert on Price Road being undersized. This culvert failed in 2005 causing the existing culvert and roadway being washed out. Both culverts are to be replaced with bridges, Price Road being a 43-foot bridge and Brentwood Drive being a 60-foot bridge.

Removal of these last two culverts on Ostrich Bay Creek will complete the removal of all City owned culverts/fish barriers from the creek.

PROPOSED SCHEDULEPriceBrentwoodCulvertReplacement_map

  • Design Started - December 2018
  • Design and Permitting Completed – Winter 2022
  • Contract Award and Order Girders – Spring 2022
  • Construction Started – June 2022
  • Construction Complete – December 2022

FUNDING

Funding is by a loan from the Public Works Trust Board and includes replacement of the culverts on Brentwood Drive and Price Road, along with the culvert on Kitsap Way. For more information on the Kitsap Way Culvert, visit the project webpage.

Total loan amount is $4,687,968

Construction cost for Brentwood and Price is estimated to be $2.3 million
Construction cost for Kitsap Way is estimated to be $1.9 million
Total design cost for all three culvert replacements is $489,988

ADDITIONAL INFORMATION

CONTACT US

  1. Gunnar Fridriksson
    Project Manager
    Ph: 360-473-5758
    Email