Price Rd and Brentwood Dr Culvert Replacements

CURRENT PROJECT STATUS UPDATE (June 7, 2022)

Construction is set to begin after the Juneteenth holiday, or June 21st. Work for the first week will be the Contractor mobilizing in, bringing in equipment and materials, and starting to clear the sites. A preliminary schedule from the Contractor is attached here.

Traffic Impacts: None currently. With work starting on June 21st, expect delays with one-lane alternating traffic and intermittent closures at both Price and Brentwood.

PriceCulvertBrentwoodCulvert
Looking northerly at the upstream culvert inlet at Price Road.
Looking southernly at the upstream culvert inlet at Brentwood Drive.

SCOPE

Both of the existing culverts for the two roadways are rated as blocking fish passage by WDFW, along with the culvert on Price Road being undersized. This culvert failed in 2005 causing the existing culvert and roadway being washed out. Both culverts are to be replaced with bridges, Price Road being a 43-foot bridge and Brentwood Drive being a 60-foot bridge.

Removal of these last two culverts on Ostrich Bay Creek will complete the removal of all City owned culverts/fish barriers from the creek.

PROPOSED SCHEDULEPriceBrentwoodCulvertReplacement_map

  • Design Started - December 2018
  • Design and Permitting Completed – Winter 2022
  • Contract Award and Order Girders – Spring 2022
  • Construction Started – Mid-Summer 2022
  • Construction Complete – December 2022

FUNDING

Funding is by a loan from the Public Works Trust Board and includes replacement of the culverts on Brentwood Drive and Price Road, along with the culvert on Kitsap Way. For more information on the Kitsap Way Culvert, visit the project webpage.

Total loan amount is $4,687,968

Construction cost for Brentwood and Price is estimated to be $2.3 million
Construction cost for Kitsap Way is estimated to be $1.9 million
Total design cost for all three culvert replacements is $489,988

ADDITIONAL INFORMATION