Create an Account - Increase your productivity, customize your experience, and engage in information you care about.
Construction is set to begin after the Juneteenth holiday, or June 21st. Work for the first week will be the Contractor mobilizing in, bringing in equipment and materials, and starting to clear the sites. A preliminary schedule from the Contractor is attached here.
Traffic Impacts: None currently. With work starting on June 21st, expect delays with one-lane alternating traffic and intermittent closures at both Price and Brentwood.
Looking northerly at the upstream culvert inlet at Price Road. | Looking southernly at the upstream culvert inlet at Brentwood Drive. |
Both of the existing culverts for the two roadways are rated as blocking fish passage by WDFW, along with the culvert on Price Road being undersized. This culvert failed in 2005 causing the existing culvert and roadway being washed out. Both culverts are to be replaced with bridges, Price Road being a 43-foot bridge and Brentwood Drive being a 60-foot bridge.
Removal of these last two culverts on Ostrich Bay Creek will complete the removal of all City owned culverts/fish barriers from the creek.
Funding is by a loan from the Public Works Trust Board and includes replacement of the culverts on Brentwood Drive and Price Road, along with the culvert on Kitsap Way. For more information on the Kitsap Way Culvert, visit the project webpage.
Total loan amount is $4,687,968
Construction cost for Brentwood and Price is estimated to be $2.3 million
Construction cost for Kitsap Way is estimated to be $1.9 million
Total design cost for all three culvert replacements is $489,988
Gunnar Fridriksson
Project Manager
Ph: 360-473-5758
Email