Create a Website Account - Manage notification subscriptions, save form progress and more.
Project work in upland areas is nearing completion and the Contractor is working on punch list items. Landscape areas will be seeded this fall, at which time the upland project phase will be complete. A second phase of the project to replace the failing outfall at the intersection of Sheridan Road and Lebo Boulevard is currently in design. Construction for the new outfall is planned for Summer 2024.
Traffic Impacts:
All project areas are currently open to traffic with no restrictions.
This project made two substantial improvements for stormwater in East Bremerton:
Olympic Manor Neighborhood – This neighborhood, in particular Dibb Street, Robin Street, and Eagle Avenue, experiences flooding caused by insufficient stormwater capacity in the system. The project corrects the flooding issue by installing new and larger pipes to increase stormwater capacity in both Robin and Eagle. Along with these system improvements, the City completed needed improvements to the downstream outfall and inlet for Stephenson Creek where these pipes connected and made roadway improvements. These improvements consist of an asphalt overlay for Eagle, complete the missing sidewalk section on the east side of Robin, and curb ramp upgrades and improving the ADA accessibility for the neighborhood.
Pine Road Stormwater Outfall – The project outfall, located near the intersection of Lebo Boulevard and Sheridan Road, is a failing. The project will replace this outfall with a new one that will dissipate energy reducing beach erosion, remove concrete debris surrounding the existing, and greatly improve the beach environment.
The stormwater portion of the project will be completed using a low interest (1.66%) Public Works Trust Fund Loan (PWTF) and be repaid over 20 years from the Stormwater Utility. The additional roadway improvements included into the project will be paid for by the Street Fund.
PWTF Total loan amount is $3,881,330
Street Fund amount is $600,000
Total Project amount is $4,481,330
Failing Pine Road Outfall and concrete debris on the beach.
Flooding from the November 2012 storm event.
July 17, 2023 – Fresh pavement on Robin Ave.
July 17, 2023 – Driveway reconstruction on Eagle Ave.
Gunnar Fridriksson
Project Manager
Ph: 360-473-5758
Email