Price Rd and Brentwood Dr Culvert Replacements

CURRENT PROJECT STATUS UPDATE (September 13, 2022)

The Contractor has placed the girders for Price Road and completed the stream restoration.  Ostrich Bay Creek now flows in the new creek bed.  Half of the girders have been placed at Brentwood Drive.

Work this week and next will be concentrating on Brentwood.  The traffic barrier on the north side of the bridge will be poured this week and traffic switched to the new bridge deck later next week.  This will allow the Contractor to remove the remainder of the existing culvert and concentrate on the stream restoration here.

Traffic Impacts: 

  • Price Road - closure in place with detours. 
  • Brentwood Drive - expect delays with one-lane alternating traffic and intermittent closures
PriceCulvertBrentwoodCulvert
Looking northerly at the upstream culvert inlet at Price Road.Looking southernly at the upstream culvert inlet at Brentwood Drive.

SCOPE

Both of the existing culverts for the two roadways are rated as blocking fish passage by WDFW, along with the culvert on Price Road being undersized. This culvert failed in 2005 causing the existing culvert and roadway being washed out. Both culverts are to be replaced with bridges, Price Road being a 43-foot bridge and Brentwood Drive being a 60-foot bridge.

Removal of these last two culverts on Ostrich Bay Creek will complete the removal of all City owned culverts/fish barriers from the creek.

PROPOSED SCHEDULEPriceBrentwoodCulvertReplacement_map

  • Design Started - December 2018
  • Design and Permitting Completed – Winter 2022
  • Contract Award and Order Girders – Spring 2022
  • Construction Started – June 2022
  • Construction Complete – December 2022

FUNDING

Funding is by a loan from the Public Works Trust Board and includes replacement of the culverts on Brentwood Drive and Price Road, along with the culvert on Kitsap Way. For more information on the Kitsap Way Culvert, visit the project webpage.

Total loan amount is $4,687,968

Construction cost for Brentwood and Price is estimated to be $2.3 million
Construction cost for Kitsap Way is estimated to be $1.9 million
Total design cost for all three culvert replacements is $489,988

ADDITIONAL INFORMATION