Marine Drive Water Main Replacement

Project Status and Schedule


The Design contract was awarded to KPG for $203,500 with engineering design completed on May 20, 2021 and project construction contract was awarded by Bremerton City Council on July 7, 2021 to Pape & Sons in the amount of #2,018,002.35. Construction is estimated to begin the week of July 19, 2021 with project paving to be completed by October 15, 2021 and total project to be concluded by November 3, 2021.

A community meeting via Zoom was held on May 3, 2021 and the presentation PowerPoint can be viewed under Related Documents.

Project Overview


The project scope includes the installation of approximately 5,800 linear feet of ductile iron water main along Marine Drive and at Rocky Point Road NW intersection. The existing water main was installed in the 1930s and is both undersized and has reached the end of its useful life. The new watermain will provide improved fire flow and service to the residents along Marine Drive. Marine Dr. will receive a full road overlay.