Reservoir 19 External Coating

Project Status (August 10, 2021)


The project was awarded on May 5, 2021 to Long Painting Company in the amount of $337,881.47. The Contractor is currently abrasively blasting the reservoir and applying the prime coat.

Project Overview


The project will recoat the external steel surface of Reservoir 19, a 2.5 million gallon above ground potable-water reservoir, located east of Harrison Memorial Center in Bremerton.

Project Schedule


Construction began on June 28, 2021 and is scheduled to be completed in early September 2021.

Photographs


Click on the link below for photos of Reservoir 19.