WWTP Headworks and Splitter Box Slide Gates

PROJECT OVERVIEW

Maintaining the operation of the Bremerton wastewater treatment plant is crucial to protect the health of the public and the environment. The Utility Division of the Department of Public Works is continuously looking for ways to improve the function of the plant and simplify maintenance. This project would install 2 new slide gates at the main intake (headworks) and replace the existing, outdated slide gates at a location in the treatment process (secondary clarifier splitter box). Both sets of gates would be electronically controlled, improving efficiency and maintenance needs.

SCHEDULE

Contract award – November 2021
Construction start – December 2021
Construction end – August 2022 (includes material procurement)

FUNDING

The project is funded by the City Sewer Utility fund and is estimated at $275,000.

WWTPSluiceGateADDITIONAL DOCUMENTS

CONTACT US

Michele Filley, P.E.
Project Manager
Ph: 360-473-2349
Email