Decommission Beach Sewer in Manette (OF-4 to EB-2)
Decommission Beach Sewer in Manette (OF-4 to EB-2)
Last Content Update:
Project Overview
Many of the residences and commercial buildings along the water in Manette between E 16th Street and the Manette Bridge are connected to a sewer main buried under the beach. This sewer main is difficult to access and maintain and can surcharge during heavy rainstorms. To address this issue, the City will be installing an upland sewer system and abandoning the beach main and lateral connections.
The project will install an upland low pressure sewer system in the vicinity of E. 16th Street and Marlow Avenue off of Wheaton Way, which will allow for the abandonment of 1,800 feet of gravity beach sewer. The beach sewer was installed in 1972 and is located between E 16th Street and the base of the Manette Bridge. An estimated thirteen (13) apartment complexes and condominiums, as well as seven (7) single family residences currently discharge to the beach sewer. The flow from these properties will be routed to the proposed upland system using grinder pump systems.
By making these improvements, the City hopes to improve the marine environment of the Port Washington narrows and reduce the need to disturb the beach environment for maintenance.
Parametrix was selected as the design consultant.
Project Status
The project was advertised for construction in May 2025. The construction contract was awarded on June 4, 2025 to Active Construction, Inc (ACI) in the amount of $4.085M. ACI started construction in July 2025.
The low pressure sewer piping and grinder pump discharge lines have been installed. The grinder pumps will arrive by mid-to-late February. Construction of Sewage Pump Station EB-7 at the end of E. 16th Street is ongoing.
Project Location
Vicinity Map
Funding
The project is included in the Wastewater Capital Improvement Plan with a budget of $6,350,000. This project is funded by two loans through the Department of Ecology Clean Water State Revolving Fund loan. The first loan is design only for $823K. The second loan is for construction for $5.18M.
Schedule
Construction started in July 2025 and is expected to be completed in July 2026.