Beach Sewer Decommissioning

Project NameConstruction Completion DateCostFeet of Beach Sewer to be Decommissioned or Removed
PAST AND CURRENT CONSTRUCTION
Eastside Beachmain ReplacementAugust 2014$1,000,0003,000
Washington Ave Sewer - N of Manette BridgeOctober 2014$1,750,0002,000
Washington Ave Sewer - S of Manette BridgeMarch 2016$1,100,0002,000
Sewage Pump Station CW-4 ReplacementMarch 2020$2,500,0001,000
Oyster Bay Beach Sewer Upgrades (OB-2 to OB-1)September 2022$7,700,0003,000
Total, Past and Current
$14,050,00011,000
PROJECT IN CURRENT 6-YEAR CAPITAL IMPROVEMENT PLAN (2023 - 2028)
Decommission Beach Sewer in Manette (OF-4 to EB-2)Anticipated 2024$4,500,0001,500
Tracyton Beachmain Conversion (Upland Sewer)**Anticipated 2024$4,700,000 0
Oyster Bay Beach Sewer Upgrades (OB-3 to OB-2)Anticipated 2028$2,400,0001,000
Oyster Bay Beach Sewer Upgrades (OB-5 to OB-2)Anticipated 2026$3,000,0003,200
Total, Current CIP
$14,600,0005,700
TOTAL, ALL PROJECTS
$28,650,00016,700

** This project is located immediately upland of a waterbody, but not on the beach. It will improve flow in 4000 feet of sewer main, thereby reducing potential sanitary sewer overflow and maintenance requirements.