The project was advertised for bid in April 2025 and bids were opened on May 13, 2025. A contract with the low bidder (Active Construction, Inc.) was awarded. The contract was executed on June 9, 2025 for the amount of $1,969,969. The City obtained funding from a Department of Ecology grant to complete final design and construction of the project. Construction began on October 27, 2025 and is anticipated to be completed by April 2026.
Scope/Purpose
In the City’s continuing effort to improve water quality for Kitsap Lake, this project will provide treatment at four outfall locations that are currently untreated. The treatment will consist of installation of TAPE GULD approved systems above the outfalls in the roadway adjacent to each site. Treatment will be for suspended solids (TSS), dissolved copper, dissolved zinc, and total phosphorus.
Schedule
Ecology grant award for final design and construction awarded – March 6, 2024
Final design completed – April 2025
Advertised for construction – April 22, 2025
Bids opened – May 13, 2025
Contract awarded – June 4, 2025
Construction Notice to Proceed Issued – August 15, 2025
Construction Material Suspension Issued – August 15, 2025
Construction start – October 27, 2025
Anticipated construction completion – April 2026
Funding
The project will be completed using the Department of Ecology grant. The grant will pay for 85% of the total cost to complete the design and construction. The Stormwater Utility will match the grant for the remaining 15% needed.